JANUARY 2021

Sunday, January 24, 2021 – Saturday, January 30, 2021
(Final Restoration Phase Activity):
  • Replacement of the concrete to repair anchor bolts on the east median barrier.

  • Repairing the existing median barrier which was damaged due to slippery surface.

  • Installation of the one missing anchor bolt for the proposed light pole.

  • Stripping, rubbing and patching the median barrier light pole pours, east of the bridge.

  • Repairing the damaged plain cement concrete (PCC) median barrier at the west end of span 1 of the north bridge and the north end of the west approach.

  • Installation of cables and grounding rods at the east approach.

  • Pulling cable and ground wire for the proposed light poles on the median barrier east of the bridge.

  • Installation of the grounding rods at all three-light pole locations.

  • Splicing and tying into the power source for the median barrier lighting on the east side of the bridge.

  • Replacement of the missing luminaires in the median barrier light poles.

Sunday, January 17, 2021 – Saturday, January 23, 2021
(Final Restoration Phase Activity):
  • Installation of the tape lane markings at the gore area and 1-295 northbound on the east side.

  • Restoration of the pedestrian crosswalk on the south side of span 1, at the south bridge.

  • Removal of the curing protection from the F-Shape barrier on the existing ramp to I-295 northbound.

  • Repainting the pedestrian crosswalk on the south side of span 1, at the south bridge.

  • Chipping and removing a portion of the double face median barrier east of the bridge.

  • Replacement of the electrical conduit that was damaged during the median barrier demo operation.

Sunday, January 10, 2021 – Saturday, January 16, 2021
(Final Restoration Phase Activity):
  • Shifting the lanes on the east end of westbound and eastbound traffic, on the east end of the project, to all the striping operation.

  • Restoration of the NPS property on the SW side of spans 1 and 2.

  • Regrading and returning the area to its original grades.

  • Forming the proposed F-shape barrier on the existing ramp to I-295 northbound.

  • Installation of pavement markings at the east side of the project.

  • Placement of concrete of proposed barrier on the south side of the existing ramp to I-295 northbound.

  • Installation of the permanent thermoplastic striping on the east end of the project.

  • Replacing the missing and/or damage wire mesh on the maintenance platform in span 1 south bridge at the west abutment.

  • Installation of the pedestrian railing on the backside of the pedestrian sidewalk at ramp C.

  • Replacing the wire mesh at two maintenance bay platforms in span 1, south bridge at the west abutment and span 1, at the north bridge at pier 1.

  • Cutting the ends of the pedestrian railing on the SE end of the pedestrian walkway.

  • Repaired the bollard at the east side under the bridge.

  • Markings of pavement at various locations at westbound and eastbound and gore areas.

Sunday, January 3, 2021 – Saturday, January 9, 2021
(Final Restoration Phase Activity):
  • Milling the existing pavement westbound east of the bridge.

  • Resetting of the existing granite stone curb on the south side of East Capitol Street eastbound.

  • Repairing concrete on the west face of pier 2, of the south bridge.

  • Patching the underside of the bridge sidewalk in span 2, at the north and south bridges.

  • Patching and parging underneath the bridge deck.

  • Resetting the existing salvaged stone curb on the south side of East Capitol Street.

  • Milling the existing AC wearing surface eastbound, east of the bridge.

  • Demobilizing sectional barges used under the bridge.

  • Removal of all boats from the site.

  • Forming the proposed barrier on the existing northbound ramp to I-295.

  • Installation of the epoxy coated rebar for the proposed barrier on the northbound ramp to I-295.