DECEMBER 2020

Sunday, December 27, 2020 – Saturday, January 2, 2021
(Final Restoration Phase Activity):
  • Prepping the concrete repairs on the west face of pier 5 north bridge, pier 4 and pier 6.

  • Installation of the electrical conduits and anchor bolts for the light pole bases on the median barrier wall.

  • Placement of concrete for the proposed median barrier at the east approach of the bridge.

  • Concrete repairs on the west face of pier 5 north bridge.

  • Prepping the under-deck concrete repair in spans 4 and 5, at the north bridge.

  • Installation of electrical conduits and anchor bolts for light pole foundation on the median barrier.

  • Concrete repairs under spans 4 and 6, at the north and south bridges.

  • Grouting the level base pad under the proposed median barrier light poles.

  • Prepping the concrete repairs on the west face of pier 3, at the south bridge.

  • Patching work around scuppers under deck concrete repair in span 4, at the north and south bridge.

  • Leveling grout around anchor bolts on the proposed light pole foundation.

  • Replacement of a door at the T base and the light pole foundation at station in the median.

Sunday, December 20, 2020 – Saturday, December 26, 2020
(Final Restoration Phase Activity):
  • Patching and parging underside of the bridge deck scuppers in span 5.

  • Hand digging, excavating and rebar installation for the proposed median barrier light poles.

  • Sawcut the control joints in the newly placed plain cement concrete (PCC) median barrier at the east approach.

  • Replacement of the navigation lighting conduit and wiring at piers 9 and 10, at the south bridge.

  • Installation of the stabilization matting on top of the existing grass on bioswale.

  • Patching and parging under the bridge and graded topsoil at the east gore and placed permanent seed.

  • Hand excavating for the proposed median barrier light poles A and B, at east median barrier.

  • Painting the existing floor grates in the maintenance platform at pier 5 and jacking angles at pier 8.

  • Patching the underside of the bridge deck and grouted the anchor bolts that were missed on pier 4, at the south bridge.

  • Installation of the junction box associated electrical conduit for the proposed median barrier light pole on the east end of the median barrier.

  • Painting yellow solid lines on the ramp to C Street.

  • Patching the underside of the proposed strip seal joint at pier 4.

  • Painting the underside of the top flange of the north fascia girder in span 8, at the north bridge.

  • Placement of permanent seed and straw mulch in the gore area east of the bridge.

  • Replacement of bolts in the existing navigation light junction box in span 10, at the north bridge.

Sunday, December 13, 2020 – Saturday, December 19, 2020
(Final Restoration Phase Activity):
  • Installation of temporary stabilization on construction entrance at north east side of the bridge.

  • Saw cutting, chipping and prepping at various locations in span 3.

  • Repaired the median barrier reinforcing steel at the east approach.

  • Replacement existing navigation light on the north face of pier 9, at the north bridge.

  • Patching operations underside of the bridge sidewalk in span 3, at the south bridge.

  • Placement of seed and temporary stabilization.

  • Completed the adjustment at the top of the reinforcing steel for the proposed median barrier east of the bridge.

  • Repairs of concrete on the west face of pier 5, of the north bridge.

  • Repairs of concrete under-deck in span 5, of the north bridge.

  • Graded bioswale at various locations and placed plant bed soil at the east approach.

  • Placement of the plain cement concrete (PCC) median barrier on the east side of the bridge.

  • Replacement and repair work on the navigational lightings.

Sunday, December 6, 2020 – Saturday, December 12, 2020
(Final Restoration Phase Activity):
  • Painting angles in span 8 and between the floor beam in spans 8 and 9.

  • Repairing under deck concrete repairs in span 9.

  • Excavating the bioswale in the median area east of the bridge.

  • Installation of epoxy coated reinforcing steel for the proposed double face median barrier east of the bridge.

  • Installation of the double conduit in the proposed median barrier wall at east of the bridge.

  • Installation of the perforated underdrain pipe for the proposed bioretention swale at the east approach.

  • Installation of the geotextile fabric on the sides of trench excavation for bioswale.

  • Placement of double washed stone bedding and encasement of the perforated underdrain pipe for the bioswale.

  • Installation of safety fence shielding.

  • Installation PVC conduit in the proposed median barrier at east of the bridge.

  • Chipping unsound concrete at east face of pier 11 in preparation for concrete repairs and patching.

  • Painting the steel superstructure in span 12.

  • Replacement of maintenance bay platform support bean in span 10 of the south bridge.

  • Installation of permanent pavement markings at the west approaches of the bridge.

  • Removal of the temporary construction entrance on the northeast side of the north bridge and loading and hauling the stone off site.

  • Patching and parging around the underside of the bridge deck scupper pours in span 3, north and south bridge.

Sunday, November 29, 2020 – Saturday, December 5, 2020
(Final Restoration Phase Activity):
  • Repair the concrete on the south face of pier 11 south bridge and west face of pier 9, at the north and south bridges.

  • Patching and parging the underside of the deck in span 1, at the north bridge.

  • Removing and replacing the steel plates on the underside of the overhead sign structure of the ramp C bridge in span 13.

  • Installation of the proposed downspouts under the new bridge deck scuppers in spans 7, 8 and 9, at the north and south bridges.

  • Completed the layout for the bioswale adjacent to the existing ramp, northbound of I-295.

  • Concrete repairs underdeck in spans 9 and 11, of the north and south bridges.

  • Installation of the junction box in median barrier.

  • Hand painting the maintenance by platform in span 10, at the north bridge and the south fascia girder.

  • Installation of the epoxy-coated rebar for median barrier.

  • Installation of the conduits in median barrier.

  • Patching under the proposed relocated maintenance by manhole in span 10, at the south bridge.

  • Painting of the rusted bolts on the south fascia girder span 1, at the south bridge.

STAY IN THE KNOW AND PLAN YOUR COMMUTE! 

Everything you need to know about DDOT I-295 construction projects in Washington DC

© 2021 DDOT